Before anyone turns up
The phone call
Basics only: which town, house or unit, which room, roughly when the place was built, and what is actually wrong. Five minutes.
The measure
About half an hour at the property. Beyond the tape measure, this is what gets looked at:
- The floor — slab or timber, and whether there is subfloor access to get under it
- The walls — whether there is sheeting that needs a sample taken
- The pipework — galvanised, copper or plastic, and where it runs
- Ventilation — whether there is a fan, and whether it actually goes outside
- Access — the driveway, steps, a unit lift, and where a skip can sit
- Ceiling and cornice condition, which tells you a lot about the room's history
- What you want — shower, bath, storage, heating, step-free entry
The quote
Written and itemised: fittings by model, tile allowance, waterproofing method, stated allowances for what an older house might hide, and a program in working days. See what it costs for the guide tiers behind it.
Approvals
Most internal bathroom work in a house is exempt development in NSW. Units generally need owners corporation approval where waterproofing to common structure is replaced. Heritage items and buildings in the Berry conservation area, or work changing external windows or walls on bushfire-prone land, may need more. Shoalhaven City Council or a private certifier confirms it.
Selections
Tiles, vanity, tapware, toilet, screen, mirror, fan, lights, heating, accessories — all chosen and ordered before the strip-out starts. This single step is responsible for more blown timelines than every other cause combined. If you are still deciding between a bath and a shower, read choosing a bath now, not in week three.
On site
Days 1–2: set up and deal with asbestos
Protection down over floors and the path to the room. If testing found asbestos, a licensed removalist takes it out first, under NSW rules, and a clearance is issued before anything else happens.
Days 2–6: strip-out
Tiles, bed, bath, base, vanity, toilet, screen and linings all out, down to frame and floor. Dusty and loud. At the end of this, everyone knows what the house was hiding.
Days 5–9: repairs and carpentry
Soft joists and bearers replaced, walls straightened, any termite damage dealt with, blocking installed for the vanity, screen, towel rails and future grab rails, and any wall changes framed. This is the stage where a decision might be needed, and where the quote's allowances get used.
Days 7–12: plumbing and electrical rough-in
New supply and waste, old galvanised pipe replaced while the walls are open, new circuits for lighting, the exhaust fan and any heating. Anything moving position moves now.
Days 11–15: sheeting and screed
Wet-area board on the walls, structural sheeting over a timber floor, and a screed that falls to the waste.
Days 14–19: waterproofing and cure
Corners and penetrations detailed, then the membrane, then time. Cure time follows the product and the weather, and Shoalhaven humidity in late summer stretches it. Photographs are taken before any tile goes on. See waterproofing and tiling.
Days 18–26: tiling
Set-out first, then floor and walls, then grout and silicone in the movement joints.
Days 25–30: fit-off
Vanity, toilet, tapware, screen, mirror, fan, lights and accessories. Plumber and electrician connect, test and certify their work.
Days 29–32: clean and handover
A proper clean rather than a sweep, a walk-through with you, a list of anything to be finished, and the paperwork: the waterproofing certificate, product details and warranty information.
Where jobs actually slip
Selections. Ninety per cent of avoidable delay. Order early, take delivery early, store it in the garage.
What is behind the tiles. Rot, termites and failed pipework cannot be confirmed until the room is open. A good quote handles this with a stated allowance and an agreed variation method, so it is a conversation rather than an argument.
Asbestos results and removalist availability. Testing takes days, and a licensed removalist has to fit you into their program.
Weather. Humidity and rain stretch the membrane cure, and wet weather makes carrying materials into a house on a steep block at Berry or North Nowra slower and messier.
Strata logistics. Approval, work hours, lift bookings and skip placement in a Ulladulla or Huskisson unit block.
Supply. A back-ordered vanity or a discontinued tile stops the job dead in the middle of it.
Living through it
If the house has a second toilet or shower, most people stay put. If it does not, plan where you are showering for three to four weeks before the job starts rather than working it out in week one — a neighbour, a relative, a caravan, or a temporary shower in the laundry if one is part of the job.
Expect dust in the first week even with protection up. Keep kids and pets well clear of the work area, especially during strip-out. Park where the trades are not, and agree at the start where the skip goes and what time work begins each day.
Doing two rooms at once
Adding a laundry or an ensuite to the same program usually adds about one to two weeks overall rather than doubling the time, because the trades come once. The reason not to do it is simple: if it leaves the house with no working shower, stage it instead. See laundry renovations and ensuites.
For a holiday let or rental
Book the work in the off-season, roughly May to August, well clear of summer, Easter and long weekends. Order everything before the vacancy starts. For a tenanted property, agree access and any rent reduction in writing under the tenancy rules. See rental bathrooms.
After handover
Run the fan every single shower and let it keep running afterwards — that is what the run-on timer is for. Wipe tapware and screen hardware down occasionally, more often within a few streets of the water. Re-seal nothing yourself in the first month; if a silicone joint needs attention, say so while the job is fresh. Keep the waterproofing certificate with your house papers, and keep the spare tiles.
Renovation work is carried out in partnership with Coastal Renovation Group, a licensed NSW builder. Licence and insurance details are provided on request.
See what it costs and questions. Call 02 4404 2684 or send the details through.
Questions people ask before they commit
How long am I without the bathroom?
Around four to five and a half weeks on site for most main bathrooms. Brick veneer on a slab with no surprises sits at the shorter end. An older fibro or weatherboard house with asbestos removal and floor repairs sits at the longer end.
What causes most delays?
Selections that are not locked in before strip-out. If the tiles, vanity or tapware are not on site when the trade needs them, the job stops and the trade goes elsewhere. After that it is what the strip-out finds, and wet weather stretching the membrane cure.
Do I need to be home?
Not every day. You need to be reachable at the start, available for a decision if something is found once the room is open, and present for the handover walk-through.
Can the work be split into stages?
Only at sensible break points, such as doing an ensuite one year and the main bathroom the next. A single bathroom cannot be half built and used in between, because the membrane and tiling have to be continuous.